Homegrown Enterprises Get A Boost In Ilocos Norte

Calling all local manufacturers and processors! The Ilocos Norte government is providing product development assistance. Apply now to boost your business.

Benguet University Eyes 100 Hectares Of Bamboo Forest

Benguet University's vision for a 100-hectare bamboo forest is a leap toward sustainable development and eco-friendly textiles.

Boracay Welcomes First Cruise Tourists Of 2025

A warm welcome to the first cruise visitors of the year as the MS AIDAstella docks at Boracay Island, ready for endless exploration.

Feel The Beat: TXT’s 4DX Concert Transports Fans Into A Dreamlike World

“Tomorrow X Together: Hyperfocus” invites fans into a 4DX world, offering an immersive experience featuring popular songs and behind-the-scenes footage. The concert runs from January 15-21 at select Ayala Malls.

Completion Of GenSan Airport Terminal Project Faces Slight Delay

The slight delay is due to the COVID-19 pandemic.
By Society Magazine

Completion Of GenSan Airport Terminal Project Faces Slight Delay

15
15

How do you feel about this story?

Like
Love
Haha
Wow
Sad
Angry

The completion of the PHP452 million new passenger terminal building of the city international airport here is facing another slight delay due to the coronavirus disease 2019 (Covid-19) pandemic.

Edgardo Cueto, manager of the Civil Aviation Authority of the Philippines (CAAP) here, said Tuesday installation of the remaining facilities of the terminal building has been stretched until September due to the late arrival of commissioned workers from Indonesia.

He said materials for the passenger boarding bridge have already arrived but it will be installed by the Indonesian supplier.

Once the workers arrive, he said they are still required to undergo mandatory quarantine for 21 days based on the protocol set by the city government.

“Hopefully the remaining components will be installed before the end of September,” he said in an interview.

Cueto said the expansion and rehabilitation of the main airport passenger terminal building are now 85 to 87 percent complete.

He said joint venture firms Vicente T. Lao Construction and C.B. Garay Philwide Builders Inc. have been working double-time to complete the project, which was previously set last May.

The construction works were partially disrupted in March due to the Covid-19 pandemic but later resumed in full swing, with the temporary closure of the city airport to commercial passenger flights.

Cueto said they cannot say yet as to when the new airport terminal will become fully operational.

“Rest assured that we are regularly monitoring its progress and necessary adjustments are being made to fast-track the process,” he said.

The airport terminal project, which started in June 2017, was part of the PHP959-million funding approved by the Department of Transportation in 2015 for the upgrading and improvement of the city airport.

It was originally targeted for completion in June last year.

The project includes the expansion of the airport’s terminal building’s arrival and pre-departure area and the improvement of basic facilities; upgrading of water supply facilities; upgrading of navigational aids; and improvement of various support facilities, including its power plant. (PNA)